Does installed cooling exceed 12 kW?
Use effective rated cooling output, not electricity consumed or a heating-mode label. Exactly 12 kW does not meet the more-than-12 kW statutory threshold.
TM44 requirements / England and Wales
Start with the installed cooling plant and who operates it, not a guessed postcode result. The correct scope determines whether an accredited air-conditioning energy inspection is required and what evidence the building needs.
Regulation 17 applies to air-conditioning systems with more than 12 kW effective rated output. When the relevant person controls the temperatures of multiple individual units in a building, those units are treated as parts of one system for this test. Exactly 12 kW is not more than 12 kW. Read regulation 17.
These questions prevent unnecessary assessments of genuinely small installations and help avoid missed obligations where several smaller systems are controlled together.
Use effective rated cooling output, not electricity consumed or a heating-mode label. Exactly 12 kW does not meet the more-than-12 kW statutory threshold.
Regulation 17 groups relevant individual units in one building when the same relevant person controls their temperatures. Establish the real system arrangement; avoid counting the same outdoor capacity twice.
The person responsible is not necessarily the freeholder or the employee adjusting a thermostat. Clarify actual technical control, landlord central plant and any separately controlled tenant installations.
The rules described here apply to England and Wales. Scotland and Northern Ireland have separate legal frameworks and should not inherit this page's inspection or enforcement assumptions.
These examples illustrate equipment grouping; they are not a compliance determination for a particular site. The actual installed rated capacity, building boundaries and technical control must always be checked.
If 7 kW is the verified effective rated cooling output and no other relevant units are controlled by the same person in that building, the more-than-12 kW condition is not met on those facts. Check the actual installed system and other duties separately.
The illustrative total is 15 kW. Where the regulation's grouping conditions apply, the installation may require accredited TM44 inspection even though each individual unit is below 12 kW. Do not double-count multi-split heads.
Do not assume the central plant report also covers separately controlled tenant installations. Establish the relevant person for each system and match the inspection report with its actual assessed equipment.
GOV.UK explains that the regulations do not contain a blanket comfort-only exemption, while its accompanying practical guidance is not intended to cover dedicated process cooling systems. Dedicated technical or process plant therefore requires individual professional assessment.
Explore the 12 kW screening questionsDo not confuse the five-year assessment interval with a fixed certificate expiry date inferred from an equipment installation invoice or a change of property ownership.
Regulation 18 sets the first-inspection date for relevant systems first put into service on or after 1 January 2008 at the end of the five-year period beginning with that first-service date. Older installations had historical initial deadlines that should not be treated as new future allowances.
Qualifying systems must be inspected by an appropriately accredited energy assessor at intervals not exceeding five years. Preserve the date of the actual accredited inspection and the complete report; an ordinary service visit does not reset this period.
Under regulation 21, when the relevant person changes and the incoming person is not given any previous inspection report, an inspection must be ensured within three months of taking responsibility. That is a specific transfer rule, not an automatic three-month grace period for every property sale.
The statutory report must come from an appropriately accredited air-conditioning energy assessor. GOV.UK recognises that supervised data gatherers may help with information collection for certain larger or complex assessments; the accredited assessor remains responsible for issuing the report.
Routine maintenance, F-Gas servicing, an EPC assessment or an internal plant checklist can supply useful supporting information, but none should be presented as the accredited TM44 inspection itself.
For England and Wales, the most recent report should identify the building, assessor, accreditation scheme, inspection date and assessed air-conditioning systems. Reports produced on or after 6 April 2012 require a valid official reference generated by register lodgement. An empty address search result on its own does not establish non-compliance.
These threshold, responsibility and inspection-timing statements are based on the Energy Performance of Buildings (England and Wales) Regulations 2012 and GOV.UK guidance. Scotland and Northern Ireland have their own arrangements. Do not copy England and Wales penalty or register rules to those jurisdictions without verifying the appropriate framework.
The report can identify opportunities involving controls, operating schedules, maintenance or system sizing. Review the recommendations against the building's actual needs before agreeing additional work. The inspection does not itself repair equipment, produce measured savings or improve an EPC rating.
Under the England and Wales inspection regime, energy-efficiency recommendations are advisory. Other safety or refrigerant duties remain separate. Keep the accredited report and any later maintenance or improvement records as distinct evidence.
Share the site address, known cooling equipment, current report and who can arrange plant access. An appropriate assessor, price, visit and report timing will be confirmed against the real system; use the quotation page to check the available submission and office contact options.
For England and Wales, check the effective rated cooling output, the building and the person controlling the system. The statutory capacity test is more than 12 kW. Establish the actual equipment and control arrangement before making a building-specific decision.
Read the applicable inspection rulesEstablish who controls the technical operation of each relevant system. The answer cannot be assumed from the job title landlord, managing agent or tenant alone. Clarify central plant, separate occupier equipment and access responsibilities before commissioning an assessment.
Review landlord and occupier responsibilityNo: exactly 12 kW is not more than 12 kW. Use rated cooling output rather than electrical consumption or a heating label, and check any relevant grouped units. Scotland and Northern Ireland use their own regulatory frameworks.
Use the initial cooling-capacity guideEngland and Wales qualifying inspections must be no more than five years apart. Record the actual accredited inspection date and review first-service or handover circumstances separately. An ordinary service visit does not reset the statutory inspection interval.
Plan the inspection renewal reviewRetrieve any existing report and establish the equipment scope and responsible person promptly. Missing paperwork or an unsuccessful register search needs investigation; it is not an automatic finding from this website. Handle any authority request and stated deadline separately.
Understand evidence requests and enforcementAn accredited air-conditioning energy inspection reviews system efficiency, controls, relevant sizing and improvement opportunities using the agreed site scope. It is distinct from routine maintenance, refrigerant leak checks and an electrical safety inspection. Read any report limitations as well as recommendations.
See what the report should containYes, where the England and Wales grouping conditions apply to individual units in the same building under the relevant person's temperature control. Confirm the control relationship and avoid double-counting outdoor capacity and indoor heads. Do not simply add every unit across an entire estate.
Understand equipment groupingDuration depends on the plant, inspection scope, records and safe access. Roof permits, multiple buildings or restricted areas can affect attendance. Agree the expected visit window when the site is scoped; the visit, completed report and lodgement are separate milestones.
Plan time and access for the inspectionTell the office the actual deadline, site location, plant and access constraints. Availability and any priority fee need confirmation by an appropriate assessor. An enquiry does not guarantee a next-day visit or a lodged report within 24 or 48 hours.
Discuss an urgent inspection requestUseful records include the cooling asset list, previous inspection report, equipment details, maintenance information and relevant operating arrangements. Identify missing records honestly. The assessor must decide what can be assessed and what limitations remain; incomplete documents are not automatically a waiver or a failed inspection.
Review the optional technical questions